Discharge of a complete Project Vessel in HONG KONG Port
Industry: Various Equipments including heavy cargoes Mode of Transportation: Project break bulk ocean freight Discharge: 301 pieces of machinery Location: Hong Kong Date: 2011
The client: A leading global forwarding company
Beyond expectations
VOLANS Shipping was contracted on a turnkey basis to discharge a complete project vessel in Hong Kong.
The 301 pieces of the project vessel were transhipped from the geared vessel onto barges within the estuary. The barges then completed a beach landing onto an VOLANS prepared landing site. The pieces were transported to the laydown area where they were offloaded to ground or staging sets. To complete this stage of the project, VOLANS utilised 3 barges, 2 tugs, 15 axles of SPMT, ancillary cranes and trailers. The final stage of this project will see VOLANS reload the pieces, transport them to site and install them onto foundations.
Correct un-lashing calculation and coordination of shore - ship operations.